Steel on the Skybridge

This month we are working on wrapping up the steel package at the sky bridge as the rest of the steel package throughout the site is largely complete. The team is currently roofing the northwest quadrant of the building and are expecting to complete roofing throughout this month.

Up next we will be moving into mechanical, plumbing, and electrical rough-ins of the east buildings and focusing on framing the walls of the west building as we get ready to transitions into rough-ins.

Site wise we are finished with gradings, curbs and we are dropping in utilities and irrigation as we get ready to begin site concrete and asphalt within the next month.