We have just received the permit and have started on the footings for the building as well as the waste slabs for forming the tilt panels that will make up the wall of the buildings. Since mobilizing a few weeks ago, we have graded the field and pre-soaked it in order to keep dust at a minimum. Currently, every part of the building is at ground level but will change quickly as well as we begin pouring tilts.

In the next few weeks, we will be working on concrete tilt panels and the underground utilities for plumbing and electrical. Our next milestone will be standing the tilt walls. As we continue to move forward with the project, we will be utilizing technology including a 3D model, drone, and 360-degree camera on this project to make construction as smooth as possible